Wolverhampton Data Centre


Project Info

PROJECT

To provide a complete ‘turnkey’ cooling solution for BT’s large Data Centre facility in Wolverhampton, West Midlands. Project included; design, manufacture, installation and commissioning of cooling system, associated control systems and management of the complete project from initial survey through to sign off.

SOLUTION

  • Install 5 off, Weatherite type 45, DX Free Cool, downflow units (Internal)
  • Install 1 off, Weatherite type 45, DX Free Cool, upflow unit (external)
  • Fully Packaged configuration
  • Free cooling damper and mixing box
  • Automatic outside air ‘free-cooling’ capabilities incorporated as standard
  • Energy efficient E C fan technology
  • Fully optimised, web enabled, control systems
  • Project Management of complete fit-out inc: cooling equipment, raised flooring configuration, associated pipe work, cabling and electrics, fire suppression system, false ceiling, etc.